Surface Transportation Program
Type of Funding: Surface Transportation Program

Award Amount: $3,649,880

Project Description*:

ARRA Amt.

Bid Date

Construction

Leonard Street – Nixon Avenue to Collindale Avenue

$1,460,000

July 10, 2009

Spring 2010

Breton Avenue – Burton Street to North City Limits

$ 300,000

July 10, 2009

Fall 2009

Fuller Avenue – Knapp Street to Plainfield Avenue

$1,029,880

 Fall 2009

Spring 2010

Hall Street – Grandville Avenue to US131

$ 150,000

 Fall 2009

Spring 2010

Hall Street – Eastern Avenue to Kalamazoo Avenue

$ 190,000

 Undetermined

Undetermined

Lake Drive – Cherry Street to Fuller Avenue

$ 230,000

Fall 2009

Fall 2009

Scribner Avenue – US131 On-Ramp to Webster Street

$ 130,000

Fall 2009

Fall 2009 or Spring 2010

Turner Avenue – 6th Street to Leonard Street

$ 160,000

 Fall 2009

Spring 2010

Total

$3,649,880

*Amounts shown are the ARRA grant amount, not the full project cost.

Note:

Securing funding for the above projects with ARRA dollars, allowed us to propose additional projects for future STPU funding. The following will now be included as STPU projects in Fiscal Year 2011*:

Federal Amt.

Breton Avenue – 28th Street to Burton Street

$ 620,000

Cherry Street – Market Avenue to Grandville Avenue

$ 70,000

College Avenue – Fountain Street to Fulton Street

$ 100,000

Hall Street – Madison Avenue to Eastern Avenue

$ 235,000

Lake Drive – Fuller Avenue to Carlton Avenue

$ 135,000

 Madison Avenue – Wealthy Street to Cherry Street

$ 160,000

Monroe Avenue – Ottawa Avenue to Leonard Street

$ 100,000

Coit Avenue – Kendalwood Street to North Park Street

$ 77,000

Total

$1,497,000

*Amounts shown are the federal grant amount, not the full project cost.

REPORTS:

October, 2009, Report to MDOT regarding Lake Drive