    ​​​Eastside Sewer Improvements Program
    Various streets near Taylor and Sweet
    Complete 2016
    Project Summary
    Taylor (Grove to Sweet), Sweet (Center to Plainfield), and Queen (Sweet Ally to Sweet) were reconstructed, including a new water main, separating the combined sewer into dedicated sanitary and storm sewers, and new curb, gutter, pavement, and drive approaches. Sidewalks and ramps were upgraded to be compliant with the Americans with Disabilities Act and installed green infrastructure such as street trees, a rain garden, porous pavement, and infiltration basins to retain and soak stormwater into the ground to filter pollutants and reduce runoff entering natural bodies of water​. Taylor was also narrowed from 42 to 38 feet wide. Work on Howland (vacated) consisted of replacing the storm sewer.

    Engagement History
    Construction Preparation
    04-11-16 at 6 p.m.
    Berean Baptist Church
    1547 Coit Avenue NE
    Grand Rapids, MI 49505

    Presentation (04-11-16)

    Concept Design Meeting
    11-10-15 at 4 p.m.
    City of Grand Rapids 
    Development Center
    1120 Monroe Avenue NW 
    Room 201 - 2nd Floor
    Grand Rapids, MI 49503
     